Peel Region homepage
Peel Region
Go
main

Dixie Road rehabilitation

100m north of Derry Road to 100m north of Britannia Road; Derry Road from Cardiff Boulevard to 400m east of Dixie intersection; intersection improvements on Dixie Road and Drew Road. Project 19-4670

Project Updates

Where is the work happening?

What are we doing?

When?

Who you can call?

Region of Peel
Contact Person Responsibilities Telephone Number
Nabiel Matta Project Manager 905-791-7800 ext. 7862
Sajmir Zesllari Site Inspector 905-791-7800 ext. 3246
Graham Bro Construction Limited
(under contract to the Region of Peel)
Kevin Hutchinson Project Manager 416-346-6843
Mike Graham Site Supervisor 905-867-0402

Staging and Working Hours

Graham Bros. Construction Limited has been contracted to complete the work on the Region’s behalf. Milling and paving operations will be staged in sections, so that lanes will only be closed on one side of the road at a time between intersections. Works will take place during the day and night, until the section is restored to base asphalt and lanes can be re-opened to traffic.

Operations will then move to the next section and will continue in this fashion until completion, weather pending. Following the winter shut-down, remaining works including top asphalt placement will take place in spring 2020. Minor works such as concrete and electrical will be done during off-peak hours (9am to 3:30pm), Monday to Friday and there will be reduced traffic lanes.

Extended working hours may cause some inconvenience to the public; however, this will help complete the project as quickly as possible.

Traffic Control

Driveway Access

Project Updates