Mississauga Road Bridge over Credit River rehabilitation
Project 14-4820
Project updates
- We have finished the work. The project is under warranty until Spring 2024.
Where is the work happening?
- On Mississauga Road, 550m north of King St.
What are we doing?
- The work includes: Conversion of existing bridge to a semi-integral bridge, removal and replacement of existing concrete bridge deck, approach slabs, barrier walls and railings, milling and paving, and landscaping
When?
- We expect to start construction in July 2021 and anticipated completion is spring 2022 (weather permitting).
Working Hours
- Belor Construction Limited has been contracted to complete the work on the Regions behalf. Hours of operation are from 7 a.m. to 7 p.m., Monday to Friday and work may also be done on Saturdays.
- These hours follow the towns by-laws. Extended working hours may cause some inconvenience to the public however will help facilitate completion of the project as quickly as possible.
Traffic Control
- The project will be phased to minimize traffic disruption while maintaining a safe working environment as required under the Occupational Health and Safety Act.
- The traffic will be maintained during construction. However, due to the nature of the work, the roadway will be reduced to a single lane controlled by traffic signals
- Emergency access will be maintained at all times.
- Please use caution when travelling through the work zone.
Driveway Access
- We will maintain driveway access as much as possible and if we need to block your driveway for a short time you will be contacted to arrange for the best time
Project Updates
- Project sketch
- The Region of Peel will keep you informed of any substantial changes in the project scope or schedule.
- Construction project updates can also be found at peelregion.ca/construction
Who can you call?
Region of Peel | ||
Contact Person | Responsibilities | Telephone Number |
---|---|---|
Jerry Tan | Project Manager | 905-791-7800, ext. 7916 |
Asad Rauf | Regional Inspector | 905-791-7800 ext. 3246 |
Construction statement regarding COVID-19
Construction is an essential service. We’re keeping employees, contractors and the community safe by complying with provincial regulations, physical distancing, using personal protective equipment, and adjusting work schedules and shifts.
Construction project updates can be found at peelregion.ca/construction. Follow Peel Public Works on Twitter for service updates and changes.
This notice was first issued on June 11 2021