Watermain replacement and improvement

Glen Erin Drive between Burnhamthorpe Road and Marshdale Court

Peel Region has been working in your neighbourhood to install watermains on Glen Erin Drive.
At this time, we have:

The remaining work has been put on hold due to the weather. We will shut down for the winter on January 22, 2024 until mid March 2024 weather dependent. We will leave the construction site in a safe condition for the rest of the winter.

Schedule for remaining construction and repair work

We expect to start work again mid March, 2024 to complete the following:

We plan to complete this work by the end of May 2024.

More details about restoration will be shared in a Spring Commencement Notice and Restoration Notice follow-up notice.  

What to expect during construction

Learn what to expect when watermain construction resumes in the spring by visiting peelregion.ca/construction/watermain and watching our short video.  The video goes behind the scenes to show what happens during and after construction.  This website also answers common questions about: 

Settlement of the ground

It is normal for repaired areas to settle a bit in the coming months. If you notice large potholes forming in the driveway, street, lawn or boulevard, please let us know and we will ensure the contractor fixes this.

Keeping you informed

We will let you know if there are any major changes to the plans.

Receive timely project updates right to your inbox by signing up for e-notices. Visit peelregion.ca/construction/signup

Water Linear Engineering
Engineering Services Division
Public Works, Region of Peel
Email: construction@peelregion.ca
Phone: 905-791-7800 ext. 4409