Retaining wall replacement
Queensway East, west of Camilla Road Crossing. Project 16-4520
We have finished the work. The project is under warranty until October 19, 2025.
Where is the work happening?
- On Queensway East, West of Camilla Road, under bridge, Cooksville Creek, City of Mississauga
What are we doing?
- The work at Queensway east and Camilla Road includes:
- Removal of three existing gabion retaining wall
- Install new armourstone wall located on the southwest embankment
- Grading and restoration
When?
- Construction Start: July 16, 2021 – Finish: July 2023 (weather permitting)
Who you can call
Region of Peel | ||
Contact Person | Responsibilities | Telephone Number |
---|---|---|
Randy Chawb-Naraine | Project Manager | 416-884-2434 |
Wood Canada Ltd. Consultant |
||
Matthew Galloway | Project Manager | 905-220-6718 |
Verti-Crete of Toronto Inc. Verti-Crete will do the work, under contract to Region of Peel |
||
Rick Lima | Project Manager | 437-215-3902 |
Working Hours
- Verti-Crete of Toronto Inc. has been contracted to complete the work on the Region’s behalf. Hours of operation are during non-peak hours from 9:00am to 3:30pm., Monday to Friday and work may also be done on Saturdays.
- These hours follow the city’s by-laws. Extended working hours may cause some inconvenience to the public however will help facilitate completion of the project as quickly as possible.
Traffic control
- The project will be phased to minimize traffic disruption while maintaining a safe working environment as required under the Occupational Health and Safety Act.
- Existing traffic flows will be maintained during construction. However, due to the nature of the work, we may require temporary curb lane closures.
- Emergency access will be maintained at all times.
- Please use caution when travelling through the work zone.
Driveway access
- We will maintain driveway access as much as possible and if we need to block your driveway for a short time you will be contacted to arrange for the best time
- We will make sure businesses have access at all times.
Project updates
- The Region of Peel will always let you know of there are any major changes to plans. We will try to disturb you as little as possible.
- Construction project updates can also be found at peelregion.ca/construction