Watermain replacement and improvement
Haslemere Avenue from Clarence Street to Centre Street South. Project 16-1340E2
Project updates
- We have finished the work. The project is under warranty until August 2019.
- August 1, 2017: Upcoming Road Paving - Haslemere Avenue (PDF)
- June 2017: Upcoming Restoration on Haslemere Ave and Centre St South (PDF)
- May 2017: Temporary Road Closure - Haslemere Avenue (PDF)
What we are doing
- Replacing and improving the aging watermain along Haslemere Avenue. View area map (PDF).
- Replacing the water service pipe to your service box.
Why
- To upgrade the water system capacity and reliability as part of the Region of Peel’s State of Good Repair program.
When
- We expect to start work on or about May 1, 2017.
- The project should be completed before September 2017. All work is under warranty for two years from the completion date.
- We will start restoring the road when all water system replacements and transfers are complete, and as weather permits.
Who you can call
Region of Peel | ||
Contact Person | Responsibilities | Telephone Numbers |
---|---|---|
Nicholas Gan | Project Manager | (905) 791-7800 x5082 |
Mark Ferreira | Inspector | (905) 791-7800 x3246 |
Sam Rabito Construction Ltd. Sam Rabito Construction Ltd. will do the work, under contract to the Region of Peel |
||
Sam Rabito | Project Manager | 905-642-5356 |
Corey Luciano | Site Superintendent | 905-642-5356 |
Working hours
- Our contractor’s normal working hours are from 7 a.m. to 7 p.m. These hours are consistent with the local municipality’s bylaws. We understand this may cause some inconvenience, but a shorter working day would mean the project would take longer to complete.
Traffic and parking control
- We may need to reduce traffic to a single lane during construction.
- If we have to reroute traffic, we will place signs giving directions.
- On-street parking will be reduced during construction.
Driveway access
- Due to construction activities, we may need to block your driveway for a short time. We will contact you before we do this to arrange for the best time and for alternate access, if needed. If your driveway is blocked, you may choose to park on a side street for a short time. If you need immediate access to your driveway, the contractor will have road plates available to quickly allow access in and out of your driveway.
- We will make sure businesses have access at all times.
- Please call the Project Manager if you have special needs related to access or business hours.
Irrigation or sprinkler systems
- Please tell the inspector if you have underground irrigation or a sprinkler system outside your property line.
- You may wish to move the sprinkler lines to inside your private property to avoid damage.
Trimming trees
- If tree branches within the right-of-way interfere with construction, the contractor will have the trees pruned before equipment enters the drip line of the tree.
- If tree branches on private property interfere with construction, they will be pruned back to the nearest suitable trunk, crotch or branch.
- The contractor will ask you for permission before cutting any branches on private property. If you do not allow the contractor onto your property to trim the branches, the branches will be cut vertically at the property line.
Interrupting your water supply
- It is our goal to let you know 48 hours (2 days) in advance if we need to shut off your water. Occasionally, we may have to reduce this notice to 24 hours.
- If we have to shut off your water because of an emergency, we will do everything we can to fix the problem as quickly as possible.
Waste collection
- Your garbage, recycling and organics containers will continue to be picked up on your regularly scheduled day. It is the contractor’s responsibility to move your garbage, recycling and organics bins to a location where our collection vehicles can pick them up. Empty containers will be returned to their corresponding addresses. Please make sure your house number is clearly marked on each bin.
Vibrations
- You may feel slight vibrations from the construction work.
Replacing and taking care of your sod
- The contractor will take care of any sod we replace for 30 days.
- You can help the sod to stay healthy by watering it for one hour in the early morning, two or three times a week. This is especially important in hot or dry weather.
- We will replace your sod as soon as we can, but there may be a short delay.
- It is very common for the work area to settle a bit following construction. If you notice any settlement, please let the project manager or inspector know and we will ensure the contractor fixes it.
Repairing your driveway
- If we need to cut your driveway to replace the existing service valve or access the watermain, we will repair the asphalt in the disturbed area from edge to edge across the driveway. Unfortunately the Regioncannotcompletely replace your driveway.
- Several weeks before the driveway restoration work, we will send you an update with contact information for the contractor, in case you wish to have the remainder of your driveway (private side) paved at the same time.
- If you have any concerns, please call the Project Manager.
- We will repair your driveway as soon as we can, but there may be a short delay.
Repairing the road, curbs, and sidewalks
- We will start restoring the road and boulevard once all replacements and service transfers are complete and as weather permits.
- We will complete the restoration on a street-by-street basis.
Closing your private well
- If you have a private well, we strongly recommend you decommission it as per Ministry of Environment and Climate Change legislation (Ontario Wells Regulation 903) upon connection to the municipal water supply. The Region of Peel has a Private Well Abandonment Program to decommission private wells on existingprivate residentialorfarmingproperties on a first-come, first-served basis, at no cost to the resident. Please visitpeelregion.ca/pw/water/water-trtmt/wellhead-abandon.htmor call 905-791-7800, extension 4685 for more program information.
- We will write to you about how to connect your property to municipal water.
Project updates
- The Region of Peel will always let you know if there are any major changes to the plans.
- We will try to disturb you as little as possible.
- Please call the project manager or inspector if you have any concerns or special needs.