Watermain replacement and improvement

Bough Beeches Boulevard, Claypine Rise, Rathburn Road, Beechknoll Avenue. Project 15-1345 C

Project updates

  • July 2020: Restoration on Bough Beeches Boulevard & Claypine Rise (PDF)
  • June 2020: Connection on Claypine Rise (PDF)
  • December 2019: Winter Shutdown on Bough Beeches Boulevard and Claypine Rise (PDF)
  • October 2019: Connection on Bough Beeches Boulevard (PDF)
  • August 2019: General Notice - (PDF)

What we are doing

Why?

When?

Who you can call

Region of Peel
Contact person Responsibility Phone number
Rene Gomez Project Manager 905-791-7800, ext. 3809
Brandon Vandemeer Inspector 905-791-7800, ext. 3246
Lancorp Construction
Lancorp Construction will do the work, under contract to the Region of Peel
Eliseo Lancione Project Manager 1-905-660-0778
Tony Vuocolo Site Superintendent 1-905-660-0778

Working hours

Traffic and parking control

Driveway access

Irrigation or sprinkler systems

Trimming trees

Interrupting your water supply

Waste collection

Vibrations

Replacing and taking care of your sod

Repairing your driveway

Repairing the road, curbs, and sidewalks