Watermain and sanitary replacement and improvement

Hanover Road, Huntington Court, Hollowood Court and Hearthstone Court. Project 19-1340D

What we are doing

  • Replacing and improving the aging watermain on Hanover Road, Huntington Court, Hollowood Court, Hearthstone Court. View area map (PDF)

Why

  • To upgrade the water system capacity and reliability as part of the Region of Peel’s State of Good Repair program. 

When

  • We expect to start work on or about July 2, 2019. 
  • The project should be completed before December 2019.  All work is under warranty for two years from the completion date.
  • We will start restoring the road when all water system replacements and transfers are complete, and as weather permits.

Who you can call


Region of Peel
Contact Person Responsibilities Telephone Number
Jimmy Cheema
Tom Graovac
Project Manager
Inspector
905-791-7800, ext. 5403
905-791-7800, ext. 3246
London Excavators and Trucking Ltd.
London Excavators will do the work, under contract to the Region of Peel

Massimo Sansone Project Manager 416-247-6601

Working hours

  • Our contractor’s normal working hours are from 7 a.m. to 7 p.m.  These hours are consistent with the local municipality’s bylaws.  We understand this may cause some inconvenience, but a shorter working day would mean the project would take longer to complete.

Traffic and parking control

  • We may need to reduce traffic to a single lane during construction. 
  • If we have to reroute traffic, we will place signs giving directions.
  • On-street parking will be reduced during construction.

Driveway access

  • Due to construction activities, we may need to block your driveway for a short time. We will contact you before we do this to arrange for the best time and for alternate access, if needed.  If your driveway is blocked, you may choose to park on a side street for a short time.  If you need immediate access to your driveway, the contractor will have road plates available to quickly allow access in and out of your driveway.
  • We will make sure businesses have access at all times.
  • Please call the Project Manager if you have special needs related to access or business hours. 

Irrigation or sprinkler systems

  • Please tell the inspector if you have underground irrigation or a sprinkler system outside your property line. 
  • You may wish to move the sprinkler lines to inside your private property to avoid damage.

Trimming trees

  • If tree branches within the right-of-way interfere with construction, the contractor will have the trees pruned before equipment enters the drip line of the tree.
  • If tree branches on private property interfere with construction, they will be pruned back to the nearest suitable trunk, crotch or branch.
  • The contractor will ask you for permission before cutting any branches on private property. If you do not allow the contractor onto your property to trim the branches, the branches will be cut vertically at the property line.

Interrupting your water supply

  • It is our goal to let you know 48 hours (2 days) in advance if we need to shut off your water.  Occasionally, we may have to reduce this notice to 24 hours.
  • If we have to shut off your water because of an emergency, we will do everything we can to fix the problem as quickly as possible.

Waste collection

  • Your garbage, recycling and organics containers will continue to be picked up on your regularly scheduled day.  It is the contractor’s responsibility to move your garbage, recycling and organics bins to a location where our collection vehicles can pick them up.  Empty containers will be returned to their corresponding addresses. Please make sure your house number is clearly marked on each bin.

Vibrations

  • You may feel slight vibrations from the construction work. 

Replacing and taking care of your sod

  • The contractor will take care of any sod we replace for 30 days.
  • You can help the sod to stay healthy by watering it for one hour in the early morning, two or three times a week.  This is especially important in hot or dry weather.
  • We will replace your sod as soon as we can, but there may be a short delay.
  • It is very common for the work area to settle a bit following construction. If you notice any settlement, please let the project manager or inspector know and we will ensure the contractor fixes it.

Repairing your driveway

  • If we damaged a portion of your interlock driveway/concrete driveway, our contractor will reinstate the damaged portion of the driveway.
  • If we damaged a portion of your asphalt driveway, we will repair the asphalt in the disturbed area by installing a temporary asphalt patch by our watermain contractor for now. The City of Brampton has scheduled Hanover Road and Huntington Court in 2020, and Hollowood Court and Hearthstone Court in 2021 for Roadway Rehabilitation, pending budget and council approval. During Roadway Rehabilitation works, a portion of most driveway aprons or at the driveway entrance (within the City right-of-way) will be disturbed again along the curb.
  • As part of the City of Brampton’s road rehabilitation in 2020 and 2021, the entire width of your driveway will be replaced from the edge of the disturbed area to the curb or to the sidewalk. During City’s resurfacing in 2020 and 2021, should you wish to have the entire or the rest of your driveway paved, you can make arrangements to have the work done at the same time with the City’s contractor.
  • For further information on the City’s Road Rehabilitation Project, please visit their website at Brampton.ca or call 311.

Repairing the road, curbs, and sidewalks

  • We will start restoring the road and boulevard once all replacements and service transfers are complete and as weather permits.
  • We will complete the restoration on all the streets once all the underground works are completed. The restoration will be temporary, as the City of Brampton plans to resurface Hanover Road and Huntington Court in 2020, and Hollowood Court and Hearthstone Court in 2021.

Project updates

  • The Region of Peel will always let you know if there are any major changes to the plans.
  • We will try to disturb you as little as possible.
  • Please call the project manager or inspector if you have any concerns or special needs.  

How did we do 

  • After we’ve finished, we will give you a postage-paid card for you to rate our work.
  • Please complete the card and mail it back to us.

Thank you!

Jimmy Cheema
Project Manager