Project 23-1310 I
Streets affected: Easement between Campobello Road and Kitimat Road.
Peel Region will be working in your area to rehabilitate the watermain on the easement between Campobello Road and Kitimat Road, as shown on the attached map. Watermains are underground pipes that bring tap water from our water treatment plants to your area. As pipes age and our population grows, we need to replace or rehabilitate older watermains to keep providing you with high quality water.
Construction schedule
Construction is planned to begin the week of September 3 and be completed by the end of September 2024. These timelines are estimates, as weather and other unexpected events may impact our timelines. All work is under warranty for two years from the completion date.
Sign up for email notices
Receive timely project updates right to your inbox by signing up for e-notices.
What to expect during construction
Learn what to expect during watermain construction by watching our short video. The video goes behind the scenes to show what happens before, during and after construction.
This website also answers common questions about:
- Why your water may be temporarily shut off,
- How traffic, parking, and waste collection may be affected,
- How driveways, roads and sod (grass) are repaired after construction is finished.
Contractor and working hours
The work will be completed by Fer Pal Infrastructure under contract to Peel Region. This contractor’s normal working hours are from 7 a.m. to 7 p.m., Monday to Friday. These hours are consistent with the local municipality’s bylaws. We understand this may cause some inconvenience, but shorter working days would require your area to be under construction for a longer period of time.
Traffic and Parking
We may need to temporarily close roads or reduce traffic to a single lane during construction. If we must reroute traffic, we will place signs giving directions. On-street parking will be reduced during construction when we are actively working on your street.
Interrupting your water supply
We anticipate that this construction project might require temporarily shutting off your water.
- It is our goal to let you know 48 hours (2 days) in advance if we plan to shut off your water for an extended period (several hours). Occasionally we may have to reduce this notice to 24 hours.
- If we must shut off your water due to an emergency, we will knock on your door to alert you, and do everything we can to fix the problem as quickly as possible.
Areas impacted by construction
Rehabilitating and replacing watermains usually requires digging a trench within the municipal right-of-way, which includes the street and the land owned by the municipality between the water service box and the street. (The water service box is a small, round, metal valve located outside on the property line between your home/business and the road.) Depending on the location of the watermain, this trench might cause temporary damage to roads, curbs, sidewalks, boulevards, lawns, and the bottom of driveways within the municipal right-of-way.
Tree protection and trimming
Trees located in the municipal right-of-way will be protected during construction using temporary fencing. If tree branches within the municipal right-of-way interfere with construction, the trees will be pruned beforehand.
If tree branches on private property interfere with construction, they will be pruned back to the nearest suitable trunk or branch. The contractor will contact you before any pruning of private trees occurs. If you do not allow personnel onto your property to trim the tree, the branches will be cut vertically at the property line.
Repairing areas impacted by construction
We will start repairing the road, curb, sidewalk, driveways, and lawns once the watermain is rehabilitated and the new water service pipes have been connected to all properties on your street.
Repairs may be delayed due to contractor availability or certain seasonal weather conditions.
For example:
- Paving cannot take place when the ground is saturated with water, or the temperature is below 3°C.
- Asphalt is not available in large volumes during the winter. Asphalt usually becomes available around mid-May.
- Most sod farms are located north of Peel. They usually have sod available beginning in late May. We will replace the sod on your property once it is available. We replace sod only until the middle of November, weather permitting, to let the sod grow roots. If we do not repair your lawn by the middle of November, we’ll replace the sod the following spring.
Repairing grassy areas
The contractor will replace any damaged sod (grass) on the boulevard or your front lawn and will take care of the new sod for 30 days. You can help the sod stay healthy by watering it. A longer ‘deep root watering’ works better to establish new sod than watering more frequently for a shorter time. Watering in the early morning allows more water to soak in instead of evaporating.
Driveway access
It may be necessary to block your driveway for a short time when crews are digging the trench for the watermain, replacing your water service box and pipe, or completing other construction activities. If so, we will knock on your door to notify you. If a trench prevents access to your driveway, the contractor will have metal road plates available to allow access if required. Whenever possible, we will work to ensure businesses can be accessed. Please contact us if you have special needs related to access.
Waste collection
If you receive waste collection from Peel Region, your garbage, recycling, and organics will continue to be picked up on your regularly scheduled day. It is the contractor’s responsibility to move your garbage, recycling, and organics bins from the end of your driveway to a location where waste collection vehicles can pick them up. Empty containers will be returned to their corresponding addresses. Please make sure your house number is clearly marked on each bin. This helps us return empty bins to the correct address.
Vibrations
You could feel slight vibrations from the construction work.
Safety during construction
Construction zones require extra caution to keep everyone safe – pedestrians, cyclists, drivers, and construction workers. When driving, walking, or biking through the construction area, please be aware of your surroundings, watch for construction crews and other road users, slow down, account for delays, and consider other routes if possible. Learn how to stay safe in construction zones.
Keeping you informed
We will let you know if there are any major changes to the plans.
We value your feedback
After we have finished, we will invite you to provide feedback on the construction project.
You can sign up to receive this survey electronically.
Thank you for your patience as we complete this necessary work. This work will allow us to continue providing you with high quality tap water. If you have any questions, please contact us.
Water Linear Engineering
Engineering Services Division
Public Works, Peel Region
Email: construction@peelregion.ca
Phone: 905-791-7800 ext. 4409