Rehabilitation of King Street

Hurontario Street to Airport Road. Project 18-4655

Project updates

  • We have finished the work. The project is under warranty until October 2020.

What we are doing

Works will include:

  • Resurfacing to improve roadway performance. The work includes, but is not limited to:
    • cold milling;
    • grading;
    • hot mix paving;
    • culvert replacements;
    • placement of pavement markings;
    • restoration; and
    • minor related works.

Where

When

  • Start: July 4 of 2018.
  • Finish: October 2018, weather permitting.

Who you can call

Graham Bros Ltd.
under contract to the Region of Peel
Contact Person Responsibilities Telephone Number
Corrado Paolini Project Manager 905-453-1200
Joey Blanchard Site Supervisor 905-965-0198
Region of Peel
Nabiel Matta Project Manager 905-791-7800 Ext. 7862
Samy Sedfawi Inspector 905-872-1862

Working hours

  • The Contractor's working hours are from 7:00AM to 5:00PM, Monday to Friday. The Contractor is permitted to work on Saturdays if they choose to.
  • These hours are consistent with the local municipality's bylaws. We understand this may cause some inconvenience; however, a longer working day would assist in shortening the project duration.

Traffic control

  • The works will be phased so as to minimize disruption to traffic while still maintaining a safe working environment as required under the Occupational Health and Safety Act.
  • Existing traffic flows will be maintained during construction. However, temporary lane closures will be required over the duration of the project. Flag persons will assist motorists through the work area.
  • Emergency access will be maintained at all times.
  • Barriers and signs will be placed for safety and direction, as required under the Occupational Health and Safety Act.

Driveway access

  • We anticipate that driveway access will be maintained in so far as possible.
  • We will make sure businesses have access at all times.
  • Please call the Project Manager if you have special needs related to access

Project updates

  • The Region of Peel will keep you informed of any substantial changes in the project scope or schedule.
  • We are committed to ensuring minimum disruption to your homes and businesses.
  • Please call the Project Manager or Inspector if you have any special needs.

Email questions or comments