Public Works Construction

Construction in Peel: Brampton and Caledon

Victoria Feedermain Project
Projects Numbers 13-1145; 12-1185;
12-1186; 12-1260; 12-1261; 12-1140; 10-1215;
08-1175; 11-1146 and 07-2250

What are we doing?

Installing various diameter watermains including the Victoria Feedermain, Mayfield Road Subtransmission watermain and local distribution works along existing road right of ways.

Why?

  • To meet the increased demand for water supply, distribution and storage needs for the north part of Brampton and the Town of Caledon.

When?

  • Contract 1 - Work on Mayfield Road between Mississauga Road and Hurontario Street began in July 2013 and is now finished. The project is under warranty until September 2017.
  • Contract 2 - Heart Lake Road between Mayfield Road and Old School Road - October 2016 to August 2018
  • Contract 3 - Heart Lake Road between Old School Road  and the future Victoria Reservoir (King Street and Kennedy Road) - October 2016 to August 2018
  • Contract 4 - Dixie Road between Mayfield Road and King Street and Old School Road Between Dixie and Heart Lake Road and King Street Between Heart Lake to Campbell's Cross School - October 2017 to August 2018

What to expect during construction?

The work will be completed using an open cut method (digging a trench and laying the water pipe in the trench) and staged to minimize disruption to traffic in the area. There may be gravel-type material and watermain piping near the roadway and heavy machinery will be used for the work. You may hear noise around the construction site.

Construction began on Mayfield Road at Mississauga Road and is proceeding east towards Hurontario Street. At the railway crossing between Van Kirk Drive and Hurontario Street crews will tunnel under the crossing and continue with open cut construction on the north side of Mayfield Road towards Hurontario Street.

Resident Notices

Other construction work

Watermain and sanitary sewer construction has begun on Mississauga Road between Bovaird Drive West and Sandalwood Parkway West. This work is anticipated to be completed by 2014.

Co-ordination with other works

As we co-ordinate works with the City of Brampton and the Town of Caledon, our work may be followed by road construction and/or resurfacing. In this case our restoration may only be temporary. When the city has finished the road work they will complete a comprehensive restoration.

Water Service Connection Fees

Once the watermains are installed, residents in some areas will have the opportunity to apply for a water service connection. Find out more about this service and the related fees.

Project Videos

Who can you call?

This project will be constructed by Varcon Construction and inspected by Region and consultant staff. The contact persons and phone numbers are listed below:

Region of Peel Personnel
Contact Responsibilities Telephone
Jaime Acosta Project Manager 905-791-7800, ext. 7922
Troy Leyburne Project Manager 905-791-7800, ext. 7919
Tom Graovac Inspector 905-791-7800, ext. 3246
Consultant - Cole Engineering
Matthew Eades Contract Administrator 905-940-6161
Jody Innes Inspector 905-940-6161
Contractor - Varcon Construction - 905-794-2041

Email questions or comments

| Back to Brampton Construction Projects |

 

Revised: Wednesday November 18 2015

www.peelregion.ca

Home | Contact Us | Search | A-Z Topic List
Privacy & Terms of Use | Service Commitment

Smaller Text Larger Text