Widening and reconstruction of The Gore Road

Queen Street to Highway 50. Project 10-4070 and 15-4080

Project update

  • We have finished the work for phase 1. Phase 1: Hwy 50 to Kelsway Circle, of this project is no longer under warranty and is complete. Phase 2: Queen St. Intersection Improvements, of this project is under warranty until July, 2022.

Scheduled work

When

South of Queen St. to Hwy 50

Queen St. Intersection Improvements

Who you can call?

Region of Peel
Contact Person Responsibilities Telephone Number
Olek Garbos Project Manager 9057917800 ext. 7827
Marc Vaccari Regional Inspector 905-791-5997 ext. 3246/47
Graham Bros. Construction Limited
under contract to the Region of Peel
Tony Mastroianni Project Manger 9054531200
Quinton Oates Superintendent 9058672099 (cell)

Working hours

Traffic control

Driveway access

Project updates

Email questions or comments